Assistants of the Andijan Institute of Agriculture and Agrotechnology, Uzbekistan, Andijan
THE ROLE OF GEODESY WORK IN THE DESIGN OF PUMP STATIONS
ABSTRACT
This article compares the benefits of using total station and traditional leveling methods for level surveying to create and update topographic plans in areas where waterworks are being built. These comparisons were evaluated on such items as preparatory work, picketing of the route, linking the route to the starting point, and leveling along the route axis.
АННОТАЦИЯ
В данной статье сравниваются преимущества использования электронных тахеометрических и традиционных нивелирных методов съемки уровня для создания и обновления топографических планов в районах, где строятся гидротехнические сооружения. Эти сравнения оценивались по таким пунктам, как подготовительные работы, пикетирование маршрута, привязка маршрута к начальной точке и нивелировка по оси маршрута.
Keywords: total station survey, leveling, tracing, survey, pump station, topographic survey, GPS-system.
Ключевые слова: тахеометрическая съемка, нивелировка, трассировка, съемка, насосная станция, топографическая съемка, GPS-система.
High yields of agricultural products largely depend on the reliable and uninterrupted operation of water facilities, including pumping stations. In recent years, great attention has been paid to improving the efficiency of water facilities and facilities. The efficiency of water facilities, including pumping stations, depends on their key performance indicators. Improving the efficiency of pumping stations, improving the design of its equipment and facilities, as well as the study of local conditions and factors that affect the efficiency of the machine-lifting complex, and the establishment of a system of scientific research.Nasos stansiyasini elementlarini joylashtirish, unumli ishlashini ta’minlash va ekspluatatsiya vaqtida foydalanishga qulay bo‘lishligi uchun quyidagi geodezik ishlar olib boriladi:
- Construction of planned and elevation geodetic substantiation (survey geodetic network) on the project area of the pump station;
- Topographic survey;
- Carrying out surface leveling and leveling works on the areas for vertical leveling;
- Creating plans (maps) and profiles;
- Drawing and design of linear structures, planning of elements of irrigation and drainage networks.
Geodetic works are of great importance in the implementation of geodetic works in the project area on the basis of the project at the level of demand.
In recent years, the introduction of modern automated tools and technologies in the field of geodesy in the design, construction and reconstruction of hydraulic structures in geodetic work and the development of results on a computer using special software, as well as graphic materials in a short time. It is known that a large amount of earthworks is carried out during the construction of collectors and drains, so the calculation of geodetic works on a modern electronic total station, and the volume of earthworks on the basis of a computer program, in turn increases productivity and saves time. causes. Therefore, we can compare traditional and modern leveling works (Figure 1,2).
Figure 1.perform measurements on an electronic total station
Figure 2. Leveling in the traditional way
From the above figures it can be seen that in the traditional method the levels have to be set at several points, while in a tacheometer we can focus from one point on all the characteristic points.
The descriptions of the time values spent for geodetic measurements performed in the area where the pump station is being designed, we consider Table 1 below to compare the results.
Table 1
Results
No |
Technology stages |
Time costs (min.) |
|
Using an electronic total station |
Using H 3 levels and roulette |
||
1 |
Preparatory work |
10 |
15 |
2 |
Divide the route into pickets |
30 |
30 |
3 |
Linking the route to the starting point |
15 |
40 |
4 |
Leveling along the track axis |
15 |
30 |
5 |
Leveling the crossbars: a) Measure the distance between the intermediate points using a tape measure b) leveling of intermediate points c) recording, drawing and checking the measurement results |
||
- |
10 |
||
10 |
20 |
||
- |
10 |
||
6 |
Manual download to computer to process measurement results |
- |
40 |
7 |
Development of measurement results, construction of transverse and longitudinal profiles |
30 |
30 |
Total time spent |
110 |
225 |
From the data presented in the table, it can be seen that a number of theoretical and practical issues related to the study of the accuracy of topographic and geodetic works carried out in the design of the pumping station and the improvement of methods using GPS-systems and electronic taximeters have been addressed.
In conclusion, it should be noted that the use of modern geodesy instruments, including electronic total stations, when designing pumping stations that serve to improve the supply of irrigation water to agricultural land, not only creates great convenience, but also saves time (40-50%), reduces workforce and improve work efficiency. Therefore, we must pay special attention to these aspects when organizing the construction of water management facilities.
References:
- Boykov V.N., Fedotov G.A., Purkin V.I. Avtomatizirovannoye proyektirovaniye avtomobilnыx dorog na primere IndorCAD/Road Moskva, 2005.
- Fedotov G.A. Injenernaya geodeziya. M., «Vыsshaya shkola», 2004.
- Oxunov Z., Yer tuzishda geodezik ishlar T., «Yangi asr avlodi», 2004
- Mamajonov, T.N.Tursunov, B.M.Shokirov, R.N.Qodirov, R.Yu.Shermatov “Nasos stansiyalaridan foydalanish” darslik 2014 y.
- Mamajanov M. Analiz ekspluatatsionnыx usloviy rabotы nasosnыx stansiy selskoxozyaystvennogo naznacheniya. Vestnik agrarnoy nauki Uzbekistana. T. 2004 g.
- Xoxlov V.A. Energosberegayuщiye rejimы rabotы nasosov i nasosnыx stansiy s dlinnыmi truboprovodami: Avtoref. dis. dokt. texn. nauk. Tashkent. IEA. 2009 g.
- Dilmrod X. et al. IMPROVING THE OPERATION RELIABILITY OF THE COMPLEX OF CONSTRUCTIONS OF THE KUYGANOR HYDRAULIC UNIT //Universum: технические науки. – 2021. – №. 10-5 (91). – С. 52-55.
- Yunusbek S., Dilmurod X., Ulug‘Bek A. FARG ‘ONA VILOYATINING EKOLOGIK HOLATNI O ‘RGANISHDA KARTOGRAFIK METODNING AHAMIYATI //Oriental renaissance: Innovative, educational, natural and social sciences. – 2021. – Т. 1. – №. 4. – С. 633-636.
- Саттиев Ю. Ш. МЕТОД ПРОВЕДЕНИЯ МАСШТАБНОГО ТОПОГРАФИЧЕСКОГО ИССЛЕДОВАНИЯ НА ЭЛЕКТРОННОМ ТАХЕОМЕТРЕ //Universum: технические науки. – 2021. – №. 11-2 (92). – С. 46-48.